Industrial.
Unit 8 New Street & Unit 8 Coity Crescent, Bridgend
Project Summary.
Client – Zurich Assurance Ltd
Location – Unit 8 New Street, Bridgend Industrial Estate
Unit 8 Coity Crescent, Bridgend Industrial Estate
Value – £192K
Programme – 9 Weeks
The project consisted of the internal and external refurbishment of two industrial units at Bridgend Industrial Estate.
The works to Unit 8 Coity Crescent included asbestos removal followed by the demolition and strip out of an internal two storey office structure. The complete rear elevation had to be dismantled and re-installed so two CNC machines could be removed from the unit by specialists. This included coordinating strip out, cladding, steelwork and CNC machine removal contractors across an 8 hour period, which took significant organisation. The works also included asbestos roof cleaning, asbestos roof repairs, UPVC window and door replacements, electrical and plumbing installations, rainwater goods replacements, a full redecoration and epoxy floor coating.
The works to Unit 8 New Street consisted of roof repairs, cladding repairs, roof coating and external decorations. The works internally consisted of strip out, electrical and plumbing installations, over-boarding ceilings and minor partition reconfiguration, soft flooring, re-decoration and epoxy floor coating.
“Very professional team, excellent communication throughout the project with a great attention to detail to deliver a high quality package of works. Great to work with and adopting a collaborative approach when resolving unforeseen works on site. Look forward to working with Creative again in the future”
Tom Short – Workman LLP
Key Trade Packages:
- Asbestos Removal & Strip Out
- UPVC Windows & Doors
- Scaffolding & Safety Netting
- Roof Coating
- Mechanical & Electrical
- Drylining
- Internal Decorations
- Roofing & Cladding
- Industrial Doors
- Steelwork