Industrial.
Units 11-15 City Business Park, Easton, Bristol.
Project Summary.
Client – LaSalle Investment Management
Location – Units 11-15 City Business Park, Easton, Bristol
Value – £505K
Programme – 16 Weeks
Following the strip out, we completed the full refurbishment of units 11-15 City Business Park as part of the landlords undertakings, prior to the incoming tenants occupation and subsequent fit out works.
M&E works, replacement ceilings, general redecorations and soft flooring works were undertaken to the office and welfare spaces, with the existing kitchenettes and WC areas also being subject to overhaul and light touch refurbishments, whilst retaining their existing fixtures and fittings.
The warehouse areas undertook a more substantial refurbishment, with full replacement of the existing M&E services, to include LED lighting installations, mechanical ventilation alterations, boiler replacements/relocations and general power works. Full redecorations were completed to the portal frames, warehouse masonry walls and cladding panels and the existing warehouse floors were finished in an Epoxy coat application.
Externally, we replaced all rooflights and a complete spray coat application to all roof sheets. Elevational areas undertook masonry repairs, spray coat applications to the existing curtain glazing, with glazing repairs and the full replacement of all steel pedestrian doors and industrial roller doors.
Key Trade Packages:
- Strip Out & Builders Works
- Rooflight Replacements
- Roof Coatings
- Small Power & Lighting
- Epoxy Floor Coating
- Internal Decorations
- Industrial Door Replacements
- Cladding & Glazing Repairs
- Soft Flooring